PROJECT OVERVIEW

To replace exising timber bridge with a stronger and wider concrete structure over Lochaber Creek on the Burnett Highway south of Eidsvold.

CLIENT NAME

Dept of Main Roads[Wide Bay Region]

TOTAL VALUE OF PROJECT

$9.76M

CONTRACT TYPE

TICO -Schedule of Rates

PROJECT DURATION

2019-2020

DETAILED SCOPE AND DESCRIPTION

ATC Consulting Engineers were involved with Main Roads to embark on a major bridge replacement project that would see effectively a new stronger and wider concrete structure being constructed.

The 78 year old wooden bridge over Lochaber Creek on the Burnett Highway south of Eidsvold was replaced with a 3 x 19m span concrete bridge including:

  • Bored Piles using screw in liners
  • Construction of columns and headstocks
  • Erection of pre-cast deck units
  • Construction of deck wearing surface and bridge barrier

During construction a temporary side-track diversion was in place to keep the Burnett Highway moving. As part of the project, a realignment and upgrade to Malmoe Road intersection, just north of the bridge, to provide better visibility when accessing the highway was undertaken.

  • Granular widening of existing approaches
  • AC and bitumen surfacing
  • Extension of existing culverts and installation of temporary culvert under side-track
  • Installation of guardrail
  • Erosion and sediment control & revegetation

The full scope of ATC Consulting Engineers involvement in the project included:

  • Project Management and Delivery
  • Contract Administration
  • Technical guidance and support to the Principal
  • Onsite Engineering supervision
  • Review quality data
  • Leadership and management of the project

PROJECT OUTCOMES

The project was a success bringing multiple benefits across a whole range or areas